Background
The issue occurs when a Qualified Person (QP) has applied and obtained clearance for PUB CSC, where QP had indicated that the relevant drainage works (internal or external) under their responsibility have been completed. The QP for the remaining drainage works is unable to apply for CSC clearance.
Status of Issue
We are currently working with the relevant agencies to improve on the submission workflow.
Recommended Workaround
QPs are advised to submit the required documents as an Independent submission to PUB (Drainage) as Submission of documents.